灌漿料的應(yīng)用領(lǐng)域可謂多種多樣,設(shè)備基礎(chǔ),結(jié)構(gòu)加固,鋼結(jié)構(gòu)柱腳,預(yù)制構(gòu)件,裝配式建筑,水利電力風(fēng)力等等,除了產(chǎn)品自身因素,施工不當(dāng)是很容易導(dǎo)致高強(qiáng)無收縮灌漿料的使用出現(xiàn)問題,如何快速找到出現(xiàn)問題的環(huán)節(jié),并快速解決,節(jié)省整個工期時間呢。下面是
濟(jì)南膩?zhàn)臃?/a>廠家為您講解過的灌漿料施工中的常見問題匯總。
The application fields of grouting materials are various, such as equipment foundation, structural reinforcement, steel structure column base, prefabricated components, prefabricated building, water conservancy, electricity and wind power. In addition to the product itself, improper construction is likely to lead to problems in the use of high-strength non shrink grouting materials. How to quickly find the problems and solve them quickly to save the whole construction period. The following is a summary of common problems in grouting material construction that Jinan putty powder manufacturer has explained to you.
01
01
缺棱掉角
Missing edges and corners
(1)模板設(shè)計(jì)未考慮防止拆模掉角因素;
(1) The template design did not consider the factor of preventing the removal of formwork from falling corners;
(2)木模未提前濕潤,澆注后木模膨脹造成高強(qiáng)無收縮灌漿料角拉裂;
(2) The wooden mold was not moistened in advance, and the expansion of the mold after pouring caused the high-strength non-shrinkage grouting material corner to crack;
(3)模板縫不嚴(yán),漏漿;
(3) Loose formwork joints and grout leakage;
(4)模板未涂刷隔離劑或涂刷不佳,造成拆模粘連;
(4) The template is not coated with isolation agent or poorly coated, resulting in adhesion during mold removal;
(5)拆模過早過猛,拆模方法及程序不當(dāng);
(5) Premature and excessive demolding, improper demolding methods and procedures;
(6)養(yǎng)護(hù)不好。
(6) Poor maintenance.
02
02
洞口變形
Deformation of the opening
(1)模內(nèi)頂撐間太大,斷面太?。?/div>
(1) The top support space inside the mold is too large and the cross-section is too small;
(2)模內(nèi)無斜頂撐,剛度不足,不能保持方正;
(2) There is no diagonal support inside the mold, and the stiffness is insufficient to maintain squareness;
(3)高強(qiáng)無收縮灌漿料不對稱澆注將模擠偏;
(3) Asymmetric pouring of high-strength non shrinkage grouting material will cause the mold to deviate;
(4)洞口模板與主體模板固定不好,造成相對移動。
(4) The fixing of the opening template and the main template is not good, causing relative movement.
![濟(jì)南膩?zhàn)臃? src=]()
03
03
錯臺
Wrong platform
(1)放線誤差過大;
(1) Excessive setting out error;
(2)模板位移變形,支模時無須直找正措施;
(2) The displacement and deformation of the formwork do not require direct alignment measures during formwork support;
(3)下層模板頂部傾斜或漲模,上層模板糾正復(fù)位形成錯臺;
(3) The top of the lower formwork is tilted or expanded, and the upper formwork is corrected and reset to form a wrong platform;
04
04
板縫高強(qiáng)無收縮灌漿料澆筑不實(shí)
Inadequate pouring of high-strength non-shrinkage grouting material for plate joints
(1)板縫太小,石子過大;放線誤差過大;
(1) The seam of the board is too small, and the stones are too large; Excessive setting out error;
(2)縫模板支吊不牢、變形、漏漿;
(2) Inadequate support, deformation, and leakage of joint formwork;
(3)縫內(nèi)雜物未清,或縫內(nèi)布管;
(3) Unclear debris inside the seam, or laying pipes inside the seam;
(4)無小振動棒插搗或不振搗或振搗不好。
(4) No small vibrating rod inserted or not vibrated or poorly vibrated.
The problems encountered in the construction of grouting materials have been explained here from these four aspects. We hope to help you. If you have any doubts or needs, please come to our website http://www.wodeapartment.com Leave a message to understand!